Limerick Rewrote Its Data Center Rules in July. The Two Projects Under Review Still Follow the Old Ones.

Anti-data center signs have gone up along Route 422. A photo caption in The Mercury shows them by the roadside. Their message is clear enough. The rulebook that applies to the two projects is less obvious.

Limerick Township supervisors adopted tougher data center zoning on July 7, 2026. The new rules lower the height cap, push buildings farther from homes and add requirements for cooling, noise testing and decommissioning. Neither project now in front of the township has to meet them. MCD7's Project Laurel on Lightcap Road and the former Publicker distillery site in Linfield were both filed while the 2024 ordinance was in effect, so that is the ordinance they must be considered under, The Mercury reported on October 7. That means the 2024 standards, and the evidence entered at each hearing, will decide both cases.

Filed hours before the vote

Project Laurel first came forward in January as an application for about 191 acres across from Philadelphia Premium Outlets. On the afternoon of July 7, just before supervisors voted on the update, MCD7 filed two more applications for the same property, according to The Mercury.

The two filings break the campus into phases:

  • Phase one: one two-story, 300,000-square-foot building at the southwest corner of the site, along Evergreen Road and Sanatoga Road.
  • Phase two: seven two-story buildings, four of 300,000 square feet and three of 400,000 square feet.
  • Equipment not counted in those totals: 72 gas-powered generators and 84 chillers across both phases, some of the chillers on rooftops.

The two phases add up to 2.7 million square feet. At the October 1 hearing, the developer's traffic engineer described the project as 2.76 million square feet. Accounts of the January plan don't agree. The Mercury's January 12 story described it as about 1.4 million square feet, and some later stories repeat that figure. The paper's July 16 story calls the January proposal 2.8 million square feet, slightly larger than the two phases combined. The developers also told the township they wanted to go ahead with hearings on the original application. The Mercury reported that it was not yet clear whether residents granted party status in that case would also be parties to the two phased filings.

The Publicker application came in earlier, in April. It calls for eight two-story buildings totaling about 1.8 million square feet on 191 acres along the Schuylkill River, with buildings as tall as 120 feet.

The 2024 rules and the 2026 rules, side by side

The comparison below draws on three sources: the township's 2024 code on eCode360, The Mercury's report on the July 7 vote, and the township's September 15 code comparison summary. That summary lists the amendments as Ordinance No. 438, approved but not yet codified on eCode360.

Standard 2024 ordinance (governs Laurel and Publicker) July 2026 amendments (future applications)
Maximum building height 120 feet in the Heavy Industrial overlay 80 feet
Distance from existing homes 400 feet, or 200 feet with noise compliance 1,000 feet, or 500 feet if sound mitigation meets the limits
Noise at property line 67 dB(A) day, 57 dB(A) night; the number does not apply during a power outage 67 dB(A)/60 dB(C) day, 57 dB(A)/50 dB(C) night, including emergency operations
Cooling and water Public central water and sewer; no closed-loop mandate Closed-loop cooling unless an alternative uses less water and energy, plus a drought-response plan
Decommissioning No provision A plan, with a fund worth 110% of the demolition cost, updated every five years
Annual sound study Not expressly required Required every year

The 2024 baseline has two complications. Ordinance 428, as first passed in June 2024, capped buildings at 60 feet and set the residential distance at 400 feet. An amendment that November raised the cap to 120 feet. The Heavy Industrial overlay also still carries its own 65 dB daytime and 50 dB nighttime limits alongside the later general rule, and the code text doesn't say which of the two controls.

The height row matters most for Publicker. Buildings up to 120 feet fit under the 2024 cap and would be 40 feet over the new one.

What the Laurel hearings have been testing

The 2024 ordinance has fewer built-in protections, so the hearing record carries more weight. Laurel's conditional use proceeding started on April 14, and the Board of Supervisors makes the decision. Before that, the Limerick Planning Commission had recommended denial unless the developer met a long list of conditions. That list included closed-loop cooling, letters confirming water supply capacity, annual sound testing, a noise baseline before construction, vibration analysis, emergency planning, consideration of non-diesel generators and a community health-impact study, Spring-Ford Press reported. Several of those conditions became requirements in the July amendments.

Each of the fall sessions has examined one part of the developer's case:

  1. September 8, fiscal impact. The applicant's analysis estimated full-buildout value at $3.16 billion. It projected annual net benefits of about $3.386 million for Limerick Township, $33.387 million for the Spring-Ford Area School District and $5.76 million for Montgomery County. Parties questioned the valuation, the staffing assumptions, costs left out of the analysis and spreadsheet errors. The analysis also did not value the three proposed substations, according to Spring-Ford Press.
  2. October 1, traffic. Traffic engineer Frank Tavani testified that the campus would generate 193 vehicle trips in the weekday morning peak hour and 138 in the afternoon peak. He relied partly on counts believed to date from January 2023, collected for an earlier warehouse and retail plan on the same site. The main entrance has been moved to Lightcap Road, opposite the signalized intersection that serves the outlets, Spring-Ford Press reported. Attorneys for the township, the school district, neighboring developers and resident parties asked about holiday and weekend traffic, fuel deliveries and generator servicing. Tavani acknowledged that no formal traffic analysis had been done for an evacuation from the Limerick Generating Station.

Power is still an open question. In July, Spring-Ford Press reported that a preliminary 2024 interconnection study found 750 megawatts could be supplied. The developer called that result no guarantee and said more review by PECO and PJM was needed.

The next Laurel session was set for October 27 at 6:30 p.m. In September, Township Manager Dan Kerr told The Mercury that the Laurel hearings "still have a long way to go."

Publicker's calendar runs into winter

The Publicker case has barely started. The township offered the developer, Limerick Town Center LLC, two hearing dates in September, and the developer couldn't make either one. The developer then agreed to extend the deadline to January 29, 2027. Kerr told The Mercury that the project should go to the planning commission in December and to its first conditional use hearing before supervisors in January. No exact dates had been set as of late September.

The township's summary of the application describes public water and sewer for domestic use only and a closed-loop cooling system. Cooling water would come from on-site wells or from an allocation permit on the Schuylkill River. Recent debris hauling at the site is not connected to the data center, Spring-Ford Press reported. The project still needs conditional use approval.

The two Limerick sites are part of a larger regional picture. The Mercury counts six active data center proposals within 44 miles of each other. Three of them sit within 10 miles of each other on either side of the Schuylkill: Laurel, Publicker and a 1.9-million-square-foot plan for the former Pennhurst property in East Vincent.

How residents take part

Because the 2024 text has looser standards, the evidence in each case matters more, and conditional use hearings have set rules for who can enter it. As Spring-Ford Press explained in its coverage of the opening session, party status lets a person present evidence, cross-examine witnesses and possibly appeal the final decision. At Laurel's first hearing, residents living within about 400 feet of the site received party status without objection. The board considered the other requests one at a time, looking at proximity and whether the person had a "direct, immediate, and substantial" interest beyond that of the general public. General public comment comes after the evidentiary portion of the case.

Location has changed too. The April session at Spring-Ford Area High School drew more than 100 people. Later hearings moved to the smaller Limerick Township Building, which officials attributed to security concerns. The township posts hearing information on its Conditional Use Hearings page.

The rulebook is still changing. On October 6, the township's engineering firm, Pennoni Associates, presented supervisors with further technical ordinance updates. Like the July changes, those updates will apply only to applications filed after they take effect.

This post is general information about township zoning and is not legal advice. If you're weighing party status or have questions about a specific property, talk with an attorney.

Glen grew up in Limerick and serves as a Limerick Fire Department Deputy Chief, so we're following these hearings as neighbors. If you own near Lightcap Road or Linfield and want to talk through what the data center calendar means for your plans, The Glen Russell Team is happy to sit down with you. Contact Us.

Work With Us

When you work with The Glen Russell Team, you gain access to exclusive programs and client-focused benefits designed to help you succeed with confidence. From flexible commission options and complimentary home staging guidance to industry-leading guarantees like the Guaranteed Sale Program and 18-Month Buy Back Guarantee, every service is built around delivering peace of mind and exceptional results. Our commitment is simple: provide a seamless real estate experience backed by proven expertise, innovative solutions, and outstanding customer care.